The Complete MIM RFQ Checklist: What Your Manufacturer Needs to Quote in 7 Working Days

Most slow MIM quotes are not slow because the supplier is busy. They are slow because the RFQ left out three things the price depends on: annual volume, which dimensions are critical, and what the surface has to look like. Each missing item turns into an email, a time-zone delay and, if nobody asks, an assumption. Assumptions are where two quotes for the same part end up 2x apart.

This checklist lists what a MIM manufacturer needs to return a firm quote within 7 working days, why each item changes the price, and what we assume when it is missing.

The core package

ItemWhy it changes the priceIf it is missing, we assume
3D model (STEP or Parasolid)Volume and mass set feedstock cost; geometry sets tool complexityNo firm quote; budgetary estimate from images only
2D drawing (PDF) with tolerancesTight tolerances may need secondary operationsGeneral tolerance ±0.5%; no critical features
Material and conditionAlloy sets feedstock price, sintering atmosphere and heat treatmentNearest MIM equivalent to the material named, quoted as an option
Annual volume and order sizeSets cavity count, tool cost and molding cost per partA middle volume, quoted at two or three levels
Program lifeSets how tooling is amortized and what tool life is neededThree years
Surface requirement per faceAs-sintered is free; polishing, PVD and plating are notAs-sintered, tumbled
Critical-to-function dimensionsDecides what must hold ±0.3% or tighter, and what gets measured per lotEvery toleranced dimension treated equally, which raises cost
Target price or current process costTells us whether to propose DFM changes or a different processQuote to the drawing as drawn

Material: name the property, not just the grade

“Stainless” is not a material callout. “17-4PH” is close. “MIM 17-4PH per MPIF Standard 35, condition H900, minimum 30 HRC” is quotable in one pass. Include:

  • Grade and standard: MPIF Standard 35 (MIM edition) or ASTM B883. If you name a wrought grade such as 303, 304 or 4140, we propose the MIM equivalent (316L, 4605 or MIM 4140) and state the property difference.
  • Heat treatment condition for hardenable grades: H900, H1025 or H1150 for 17-4PH; hardened and tempered for 420 and 440C.
  • Functional requirements that limit the choice: corrosion test hours (ASTM B117), non-magnetic behavior (a relative permeability limit), biocompatibility, food contact.
  • Minimum density if it matters to function, for example ≥ 7.60 g/cm³ for 17-4PH per ASTM B962.

Volume: give the real numbers, and the uncertainty

Volume decides the tool. At 5,000 pieces a year, a one-cavity tool is usually right. At 500,000, a four- or eight-cavity tool pays back quickly. Give:

  • Annual volume for year one and at peak
  • Typical order quantity and how often you order
  • Program life in years
  • Prototype and pilot quantities if you need them before production

If the forecast is uncertain, say so. We will quote two or three volume tiers rather than guess.

Tolerances: mark what matters

As-sintered MIM holds about ±0.3% to ±0.5% of nominal because every part shrinks 15% to 20% linearly in sintering. A drawing that applies ±0.02 mm to every dimension, because that is the title block default for machined parts, forces a quote full of secondary operations. Mark:

  • Critical-to-function dimensions (often three to five): these are measured per cavity at first article and monitored in production.
  • The datum scheme, matching how the part locates in your assembly.
  • The general tolerance for everything else, for example ±0.5% or ISO 2768-m.

Surface and appearance: per face, not per part

Most MIM parts have one cosmetic face, or none. Specify per face:

  • As-sintered (about Ra 1.6 to 3.2 µm), tumbled, bead blasted, polished (Ra value) or mirror
  • Coating or plating: type, thickness, color reference
  • Where gate marks, ejector marks and parting lines are allowed
  • The cosmetic inspection standard: lighting, distance and defects allowed by zone

Assembly context and approvals

  • Mating parts, press fits, threads and load-bearing features. A short note on how the part is used often changes the DFM advice more than any dimension does.
  • Approval route: FAI, PPAP level, material certificates, RoHS or REACH declarations, and any customer-specific quality requirements.
  • Packaging if parts are cosmetic or fragile: trays, interleaving, count per bag.
  • Destination and Incoterms (EXW, FOB, DDP) if you want landed pricing.

What a complete quote should contain

A quote built on this package should come back with every assumption visible. Ours is structured as a tiered quote:

LineWhat it states
DFM reviewFeatures driving cost or yield risk, and proposed changes with reasons
Prototype tool and samplesTool cost, tool lead time (4 to 5 weeks), sintered samples 10 to 15 working days after the tool is ready, sample quantity
Pilot lotQuantity, price, lead time
Production toolCavity count, tool life in shots, lead time (confirmed with you after sample approval), ownership
Piece priceAt each volume tier, with the yield basis stated, including any sizing or other secondary operations after sintering
Secondary operationsEach one on its own line: heat treatment, machining, finishing
InspectionWhat is measured, how often, and what documents ship with each lot
Lead timesRepeat-order lead time and any holiday-period constraints

Red flags in a MIM quote

  • No cavity count or tool life stated. You cannot compare tooling cost without them.
  • No yield or density basis. The price may assume yield the geometry cannot reach.
  • “All tolerances per drawing” with no comment on a drawing full of ±0.02 mm callouts. Either secondary operations are hidden in the price, or they will appear after T1.
  • A tool price far below the market with no mention of steel grade or cavity count.
  • No DFM comments at all on a part first designed for machining. Either nobody looked, or the comments come later as change orders.

Common RFQ mistakes

  1. Sending a drawing made for CNC without marking which tolerances matter.
  2. Giving only “samples” quantities when the decision depends on production price.
  3. Naming a wrought material without the property that drove the choice.
  4. Leaving cosmetic requirements to the sample review, after the tool is built.
  5. Not saying the part is still changing. A prototype tool is the right step in that case, and the quote should reflect it.

Send the package

Use the lists above as your RFQ template. Send the STEP and drawing, material and condition, volumes, critical dimensions, and surface requirements. If you need an NNN agreement first, ask and we will send one. Within 7 working days you get a free DFM review and a tiered quote: prototype tool (4 to 5 weeks) and sintered samples (10 to 15 working days after the tool is ready), a pilot lot, and production pricing at your volumes, with every assumption written down so you can compare it line by line with any other quote.